OSRAM SYLVANIA

Back to Our Work

HCC created the cleanroom envelope in an existing plant, with insulated metal panel exterior walls and plenum cap, as well as Power-T ceiling grid to make it a walkable system.

The plenum support system, ceiling grid, and ceiling tiles, were all able to support a man load so service could be performed above the ceiling.

HCC installed new epoxy floors, HVAC controls, electrical, process piping, an air shower, and pass-thru.

HCC provided a new dedicated make-up air system to control pressure and humidity, with a new humidifier fed from a new dedicated RO water system.

A new sensible cooling recirculation unit was installed to cool the process load. The unit did 75% of the rooms recirculation air and was supplemented with 4×4 fan filter units, with ECM motors.

  • LOCATION

    Exeter, NH
  • INDUSTRY

    microelectronics
  • PROJECT TYPE

    Design/Build
  • ISO CLASS

    ISO 7
  • SIZE

    3,000sf
  • PROJECT SCHEDULE

    3 months
  • PROJECT COST

    $1,200,000